In Textile and Apparel industry, we use different types of calculations. In this article, we are going to learn some of the basic sewing line calculations.
1. Efficiency = Output/Input
= (SMV*Product Quantity) / (Worker*Working Hour*60)
= [(38.50*700) / (60*10*60)]*100
= 74% (Line Efficiency)
Here,
SMV=38.50
Working hour=10
No. of worker=60
2. Target/hour = (60/SMV)*Efficiency%
= (60/0.85)*70%
= 50 pcs/hour (worker)
Here,
SMV=0.85
Efficiency=70%
= (60/0.85)*70%
= 50 pcs/hour (worker)
Here,
SMV=0.85
Efficiency=70%
3. Target/line = [(No of worker*working hour *60)/SMV]* Efficiency%
= [(75*10*60)/23.5]*60%
= 1150 pcs
Here,
No of workers=75
Working hours=10
SMV=23.5
Efficiency=60%
= [(75*10*60)/23.5]*60%
= 1150 pcs
Here,
No of workers=75
Working hours=10
SMV=23.5
Efficiency=60%
4. Required days for the schedule = Total order quantity / Average target
= 50000/2000
=25
Here,
Average target=2000
Order quantity=50000
= 50000/2000
=25
Here,
Average target=2000
Order quantity=50000
5. CM of garments= (Total Production)/(no of worker*work hour)
= 250000/(1500*10)
=1.66 BDT
Here,
Total Production=250000
No of workers= 1500
= 250000/(1500*10)
=1.66 BDT
Here,
Total Production=250000
No of workers= 1500
6. Factory capacity = [(Work hour*total workers*working day*60)/SMV]*Efficiency %
= [(10*1500*26*60)/14.13]*55%
= 8,28,025 pcs/month
= [(10*1500*26*60)/14.13]*55%
= 8,28,025 pcs/month
7. Others
• Basic time = Observed time * Rating
• Observed time = Total Cycle time / No of cycle
• Rating = (Observed Rating * Standard rating) / Standard rating
• Factory capacity = (Work hour / SMV) * Total worker * Working day * Efficiency
• Required no of operator = Target daily output / Daily output per operator
• SMV = Basic time + Allowances
• Machine Hour Rate = Actual Factory overhead cost/Actual Machine working hour
• Line Labor Productivity=(total no. of output per line per day)/ no of worker worked.
• Line m/c productivity= (total no of output per line per day)/ no of machine used.
• Capacity = no. of m/c operators X working minutes x efficiency x presents %
• Load = Contract Size X Work Content (Total SMV of the Garment)