Important Sewing Line Calculations

Important Sewing Line Calculations

In Textile and Apparel industry, we use different types of calculations. In this article, we are going to learn some of the basic sewing line calculations. 

1. Efficiency = Output/Input 

                    
  = (SMV*Product Quantity) / (Worker*Working Hour*60)

                      = [(38.50*700) / (60*10*60)]*100

                      = 74% (Line Efficiency)

Here,
SMV=38.50
Working hour=10
No. of worker=60 

Textile Gems


2. Target/hour = (60/SMV)*Efficiency%
                        = (60/0.85)*70%

                        = 50 pcs/hour (worker)

Here,
SMV=0.85
Efficiency=70%

3. Target/line = [(No of worker*working hour *60)/SMV]* Efficiency%
                       = [(75*10*60)/23.5]*60%

                       = 1150 pcs

Here,
No of workers=75
Working hours=10
SMV=23.5
Efficiency=60%

4. Required days for the schedule = Total order quantity / Average target
                                                      = 50000/2000

                                                       =25

Here,
Average target=2000
Order quantity=50000 

5. CM of garments= (Total Production)/(no of worker*work hour)

                               
= 250000/(1500*10)

                               =1.66 BDT

Here,
Total Production=250000
No of workers= 1500

6. Factory capacity = [(Work hour*total workers*working day*60)/SMV]*Efficiency %
                                = [(10*1500*26*60)/14.13]*55%

                                = 8,28,025 pcs/month 
7. Others
       Basic time = Observed time * Rating
       Observed time = Total Cycle time / No of cycle
       Rating = (Observed Rating * Standard rating) / Standard rating
       Factory capacity = (Work hour / SMV) * Total worker * Working day * Efficiency
       Required no of operator = Target daily output / Daily output per operator
       SMV = Basic time + Allowances
       Machine Hour Rate = Actual Factory overhead cost/Actual Machine working hour
       Line Labor Productivity=(total no. of output per line per day)/ no of worker worked.
       Line m/c productivity= (total no of output per line per day)/ no of machine used.
       Capacity    = no. of m/c operators X working minutes x efficiency x  presents %
        Load     = Contract Size X Work Content (Total SMV of the Garment)